Innovative Temporary Shoring System

Our 1st innovative soldier pile system design using steel I-beam and sheet pile at one of our Johor project sites in Electrified Double Track project.

Excavation below ground level is required for construction of reinforced soil wall of approach bridge abutment. The total excavation depth is about 6.6m and located beside the existing road.